About the Project

WHAT IS A CAPITAL IMPROVEMENTS PLAN

This Plan (CIP) is a blueprint for identifying the City’s capital (infrastructure/equipment) needs, priorities, and estimated costs.  The plan also provides viable funding options for these capital projects.  The objective of the CIP is to create a logical, transparent, data-driven strategy for investing in the City’s infrastructure needs.  The Plan strives to reflect the priorities of City residents and to exemplify sound financial practices.  

The CIP process consists of six basic steps:

  • * Inventory and evaluation of infrastructure, facilities, and equipment.
  • * Advice and guidance from residents on priorities.
  • * Prioritization of needs.
  • * Identification of funding options to meet the needs.
  • * Matching funding sources with improvements.
  • * Formal adoption and use by the City Council.

The process provides an orderly and routine method of identifying and financing capital improvements and makes capital expenditures more responsive to the needs of residents by informing and involving them in the process. Thus, the CIP process should ultimately save the City financial resources.

While much of the City’s budget and financial planning efforts are by necessity focused on one or at most two-year intervals, capital planning can still help focus attention on the City’s long-term objectives and financial capacity.  This will help balance operating and capital needs. Like many communities in Montana, Havre is often faced with the option of reducing its capital plan objectives in order to balance the operating budget. A formal and adopted capital improvements plan will help to maintain a consistent level of spending for capital needs, barring any unforeseen events.

PROJECT SCHEDULE

2022

PASER Analysis

Start: 10/1/2022                  End: 05/15/2023

Oct 1, 2022
2023

Kickoff Meeting

Start: 02/13/2023                  End: 02/13/2023

Feb 13, 2023

Inventories and Information Gathering

Start: 2/14/2023                 End: 4/28/2023

Feb 14, 2023

Public Outreach Survey

Start:  4/15/2023                 End: 5/31/2023

Apr 15, 2023

Meeting with City Departments

Start: 5/14/2023                  End: 5/19/2023

May 15, 2023

Department Leads Provide Information

Start: 05/21/2023                  End: 06/15/2023

May 21, 2023

Analysis of Data

Start:  6/15/2023                   End: 8/31/2023

Jun 15, 2023

Draft CIP

Start: 09/01/2023                  End: 10/15/2023

Sep 1, 2023

Meet with City on Draft CIP

Start: 10/22/2023                 End: 10/27/2023

Oct 22, 2023

Public Input on Draft CIP

Start: 11/5/2023                End: 11/30/2023

Nov 5, 2023

Final CIP

Start: 12/1/2023                 End: 12/31/2023

Dec 1, 2023
2024

Project Closeout

Start: 01/01/2024                 End: 01/31/2024

Jan 31, 2024